The Rambler: Part II

The first phase of Reading 2100’s restoration is complete, but we’ve still got work to do. Here’s an update on restoring The Rambler. [button open_new_tab=”true” color=”accent-color” hover_text_color_override=”#fff” size=”medium” url=”www.fireup2100.org/donate” text=”DONATE” color_override=””]

Roundhouse Work Session Report for – September 3rd, 2016

Work Report Saturday proved to be an interesting and challenging day.  Preparation began to remove the oil tank from the tender.  The steam piping and electric cable was removed from the top of the tank and fittings installed for the salvage company to drain the oil.  

Roundhouse Work Session Report for – July, 2016

Work Report We had an interesting day that started out with some corrective issues.  Contractor Dan Pluta joined us and reviewed our current progress.  We discussed several things including trying to resolve the air leak in the dry pipe.