May 2021 Update

With your help, we’re delighted to say that last month we passed a significant milestone with the restoration of Reading 2100. Thanks to your donations, over 550 staybolts were welded into the firebox of the locomotive. In this video update, Jason Johnson of Gemini Industrial Machine explains the welding process. Other work done by volunteers May 2021 Update

Fire Up 2100! Febuary 2021 Update

https://youtu.be/yWoa7Mcwyhk American Steam Railroad President Rob Gardner gives you an update on the recent work done on Reading 2100, including: Work has continued this winter with the ultrasound survey of the boiler. This necessary process is part of the 1472-day inspection required by the Federal Railroad Administration. The boiler has been gridded off, and readings ... Fire Up 2100! Febuary 2021 Update

Fire Up 2100! Year in Review: 2020

   This year has been full of challenges and is one like no other we’ve experienced in a long time. For American Steam Railroad, it was one where you, the supporters, have shown through these difficult times. In the past 12 months, volunteers have given over 1,800 hours to help with the restoration of Reading Fire Up 2100! Year in Review: 2020

November 2020 Fire Up 2100! Update

https://www.youtube.com/watch?v=YcFAAQ5aWww     American Steam Railroad treasurer Forrest Nace fills you in on what has been accomplished in the past month on Reading 2100. Highlights include: The work to complete material blasting the 560 staybolts has continued on from last month. We're using a fine glass substance that auto body shops use, this allows us ... November 2020 Fire Up 2100! Update

September 2020 Restoration Update

Here is the mid-month update on what’s been accomplished by American Steam Railroad volunteers. The forging and machining of the 560 staybolts has been completed by our great volunteers, who have given many hours and days to this project. The next process is to sand blast all of them to remove mill scale so they September 2020 Restoration Update

Fire Up 2100 Mid August Update

Here is the mid-month update on what’s been accomplished by American Steam Railroad volunteers. The forging and machining of the 560 staybolts has been completed by our great volunteers, who have given many hours and days to this project. All the telltale holes have been drilled in the center of the staybolts, the next process Fire Up 2100 Mid August Update

August 2020 Restoration Update

American Steam Railroad’s Communication Director Brian Smith fills you in on what’s been accomplished in the past month in the latest video update. Highlights include:

Black Diamond Birthday T-Shirt Contest

Calling all artists! We’re celebrating 2100’s 75th birthday this year in grand style. To mark her Black Diamond Birthday this September, we’re holding a t-shirt design contest to commemorate this special occasion. The winner of the contest will get $100, a one-year membership to American Steam Railroad, and a shirt featuring the winning design! The Black Diamond Birthday T-Shirt Contest

Doyle McCormack Dinner Postponed

We regret to inform you that the Legends of Steam dinner with Doyle McCormack on Sept. 19 has been canceled for this year. Those holding tickets have already been notified of the cancelation. After much discussion with the Mad River & NKP Museum, and reviewing protocols by local and state health departments, both organizations have Doyle McCormack Dinner Postponed

Fire Up 2100 Mid July Update

Here is the mid-month update on what’s been accomplished by American Steam Railroad volunteers. If you’d like to volunteer, become a member today and you’ll be able to help us bring steam back to the high iron.